Dawsons Siding Rd, Dulverton was an excellent choice to establish DWM’s regional waste treatment site, in late1994.

In late 1994 four cooperating councils in the Cradle Coast region opened the regional landfill at Dulverton on Dawsons Siding Rd to service the Mersey-Leven area. The councils were Devonport, Central Coast, Latrobe and Kentish, and it is a testament to regional cooperation in the area.

Dulverton was an excellent choice as the site has clay soils, this offers a great starting point to ensure the surrounding environment is protected.

The DWM landfill site has been scientifically designed to operate efficiently and protect the soil, water and air quality of the Tasmanian environment.

The landfill is constructed as a series of cells. The site of each cell is first levelled with a slight incline to ensure all liquid drains in the same direction. Cells are precision-engineered to encourage any moisture coming from the waste to drain into a specially constructed and HDPE-lined leachate pond.

Waste from municipal and other sources goes into the working area of the cell and is spread evenly to about 300mm before being compacted.  

The DWM landfill was the first in Tasmania to implement machine guidance for its landfill compactor.  This technology has improved the landfill’s waste compaction density and operational efficiency, and reduced surveying costs.

DWM landfill cells now feature geo-synthetic clay lining and have a manufactured hydraulic barrier of natural sodium bentonite and geotextiles to safely contain and direct moisture.

Leachate control is one of the most important aspects of landfill management and involves safely containing and transferring leachate via 7kms of pipeline into the sewerage system for safe processing.

After waste in a cell is compacted, it is covered with a layer of inert material such as soil, sand or crushed glass to minimise odour and the risk of rodents. The waste cell is built up layer by layer until it reaches its maximum height, then it is capped with a layer of clay to prevent rain from entering the waste hill and topped with soil before being revegetated.

For a full-size image, click on the graphic below:

Creation of landfill cells at the Dulverton site is pictured below: